Hi we have found that if the team are delivering their sprint story point commitments then there is little point in adding the effort of breaking stories into tasks and estimating those as well. The latter really only becomes useful when your team is regularly not meeting their commitment. Then breaking stories to tasks and looking at a sprint burn down in detail may help them understand what they may be missing in their story point estimation.